Transport for London reply
to our concerns on new trains
We wrote back in June to TfL on their plans to upgrade trains on the
Metropolitan Lane from late 2009, and also heard a presentation from
them at our AGM in June. A lot of the implications for an efficient
service stem from a new signalling system – line speed, capacity
and managing an increase in peak service through Baker Street.
They say they’re re-negotiating the signalling contract because
of the Metronet administration. They want better value for money and
an improved design. But it doesn’t inspire confidence when it’s
only just over a year until the first new train is due – they
now say early 2010 – and they say the contract won’t now
be awarded until summer 2010. So now it’s even more confusing
about what’s going to happen when.
Shown below is a question and answer exchange which followed after
the AGM. I’ve also added in some extra comments to show our
reaction.
When the number of trains per hour is increased, how will
the logistical implications be managed? (E.g. signals, platform capacity,
line sharing with the Chiltern Turbo)
New signalling is being designed specifically to allow an increase
in the number of trains, and will be fully compatible with the Chiltern
trains. As each new train has roughly the same capacity as an existing
train, we do not envisage a need for platform capacity enhancements.
Questions on Chiltern trains are best addressed directly to them.
(Our comments – peak services are included in Chiltern’s
timetable starting December 08, at the same times as now 06.59 and
08.03)
With the planned increase in the number of trains on the Metropolitan,
Circle and Hammersmith and City Line, how do you plan to get all the
extra trains through Baker Street?
The new signalling system will be designed to accommodate the
increased number of trains.
(Our comments - the question is how? Surely there are some general
principles without specific details relevant to an individual design
contract? They add that the requirements of the contractor will be
clear, the system designed to meet these and all junctions will be
assessed to make sure they reach desired capacity. But it’s
nearly two years until they will have re-awarded the signalling contract
and new trains are arriving before that, so we’re hardly convinced
that it’s in hand.)
It’s been said the timetable will not change until old
trains have gone and the new signalling system is in place. The problem
is the four year changeover period and new signals not working until
2012. So does that mean a gradual reduction in seats until the new
timetable starts?
Careful planning work will be carried out to minimise inconvenience
during changeover, however, we have not yet finalised the timetables
that will operate during changeover, and once the upgrade is completed,
so it’s not yet possible to exactly how many seats will be available
at various stages.
(Our comments – so no real answer to this question either.
But at least they have admitted since our original exchange of emails
on this issue that there will be a reduction in seat numbers during
the changeover. They also argue that their timetabling process is
robust with publication in good time. But what does that mean? Our
interpretations of “good time” could be very different!)
We’re confused over capacity. You say each new train
will have 70% of the seats of the trains used now. When operating,
the increase in frequency will mean a 30% increase in hourly capacity,
but only 98% of the current seats. Can you show us your calculations
so we know how these figures relate to each other?
The future number of seats per hour will depend on capacity and
service frequency. Frequency will in turn depend on the new signalling.
With a new design the figures given previously will not necessarily
reflect future capability. At this stage we do not yet have any updated
figures for the number of seats per hour.
(Our comments – so we’re as confused as we were before.
We’re not far off new trains without any idea how they will
be managed. And the original capacity figures are theirs, but now
they can’t give any context to them. So why tell us in the first
place? They’ve since said these figures applied to the previous
signalling contract and are no longer relevant, but surely the capacity
plans should be more or less consistent – with the signalling
contract awarded on this basis to deliver the capacity plans, rather
than the signalling contract determining what the capacity plans should
be?)
What will be maximum speed limit be on the line once the new
stock has been introduced and how much will the travelling time then
reduce by?
Speed limits are determined more by signalling and track condition
than by trains. We will not have definite information about final
maximum speed limits until the redesign and re-tender of signalling
has ended. But they are planned to be close enough to 62mph and will
vary.
(Our comments – so it’s the signalling contract again,
although at least the figure on speed is the same as what we published
in the last issue of Independence)
So these were the questions of most interest to us. But we did ask
others, on step-free station access, what they would do if the air
conditioning stopped working, platform lengthening, noise studies,
anti social behaviour/security measures and use of under seat luggage
racks. Anyone wanting further details should email feedback@rickmansworth-residents-association.org
Russell Carpenter